ITAC Assessment: LE0153
ITAC logo
ITAC Assessment: LE0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Men's Suit
NAICS 315210: Cut and Sew Apparel Contractors
SIC 2311: Men's and Boys' Suits, Coats, and Overcoats
Sales Range $10
M
to 50
M
# of Employees 324
Plant Area 103,925
ft2
Annual Production 139,000
pieces
Production Hrs. Annual 2,592
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,324 2,378,334
kWh
Electricity Demand $114,170 9,994
kW-mo/yr
Natural Gas $84,290 13,496
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,478 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,879

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7131: Add area lighting switches $3,181 $1,375 $1,537
55,296
kWh
$1,644
-
kW-mo/yr
- -
02 2.7233: Use properly designed and sized hvac equipment $4,007 $4,000 - - $4,007
-
MMBtu
-
03 2.2511: Insulate bare equipment $19,979 $7,500 $6,345
278,572
kWh
$13,634
-
kW-mo/yr
- -
04 2.2442: Preheat combustion air with waste heat $2,432 $1,500 - - $2,432
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $4,189 $750 - - $4,189
-
MMBtu
-
06 2.7442: Keep doors and windows shut when not on use $4,948 $1,000 $1,187
42,690
kWh
$3,761
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $766 $75 $263
9,400
kWh
$503
-
kW-mo/yr
- -
08 2.7111: Reduce illumination to minimum necessary levels $1,976 $877 $472
16,848
kWh
$962
-
kW-mo/yr
- $542
TOTAL RECOMMENDED $41,478 $17,077 $9,804
402,806
kWh
$20,504
-
kW-mo/yr
$10,628
-
MMBtu
$542
TOTAL IMPLEMENTED $11,879 $2,702 $1,922
68,938
kWh
$5,226
-
kW-mo/yr
$4,189
-
MMBtu
$542
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs