Assessment Year | 2003 |
---|---|
Principal Product | Men's Suit |
NAICS | 315210: Cut and Sew Apparel Contractors |
SIC | 2311: Men's and Boys' Suits, Coats, and Overcoats |
Sales Range | $10 M to 50M |
# of Employees | 324 |
Plant Area |
103,925
ft2
|
Annual Production | 139,000
pieces
|
Production Hrs. Annual | 2,592
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,324 | 2,378,334 |
kWh
|
$0.076 |
Electricity Demand | $114,170 | 9,994 |
kW-mo/yr
|
$11.42 |
Natural Gas | $84,290 | 13,496 |
MMBtu
|
$6.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,478 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,879 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7131: Add area lighting switches | $3,181 | $1,375 |
$1,537
55,296
kWh
|
$1,644
-
kW-mo/yr
|
- | - | |
02 | 2.7233: Use properly designed and sized hvac equipment | $4,007 | $4,000 | - | - |
$4,007
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $19,979 | $7,500 |
$6,345
278,572
kWh
|
$13,634
-
kW-mo/yr
|
- | - | |
04 | 2.2442: Preheat combustion air with waste heat | $2,432 | $1,500 | - | - |
$2,432
-
MMBtu
|
- | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,189 | $750 | - | - |
$4,189
-
MMBtu
|
- | |
06 | 2.7442: Keep doors and windows shut when not on use | $4,948 | $1,000 |
$1,187
42,690
kWh
|
$3,761
-
kW-mo/yr
|
- | - | |
07 | 2.7135: Install occupancy sensors | $766 | $75 |
$263
9,400
kWh
|
$503
-
kW-mo/yr
|
- | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $1,976 | $877 |
$472
16,848
kWh
|
$962
-
kW-mo/yr
|
- | $542 | |
TOTAL RECOMMENDED | $41,478 | $17,077 |
$9,804
402,806
kWh
|
$20,504
-
kW-mo/yr
|
$10,628
-
MMBtu
|
$542 | ||
TOTAL IMPLEMENTED | $11,879 | $2,702 |
$1,922
68,938
kWh
|
$5,226
-
kW-mo/yr
|
$4,189
-
MMBtu
|
$542 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs