Assessment Year | 2006 |
---|---|
Principal Product | Printed Corrugated Containers |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $5 M to 10M |
# of Employees | 17 |
Plant Area |
85,000
ft2
|
Annual Production | 11,000,000
lb
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $16,625 | 828,800 |
kWh
|
$0.020 |
Electricity Demand | $73,158 | 4,800 |
kW-mo/yr
|
$15.24 |
Natural Gas | $6,980 | 694 |
MMBtu
|
$10.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $165,141 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,170 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $901 | $215 |
$193
9,725
kWh
|
$708
-
kW-mo/yr
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $581 | $163 |
$121
6,074
kWh
|
$460
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $371 | $25 |
$80
4,000
kWh
|
$291
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $155 | - |
$33
1,657
kWh
|
$122
-
kW-mo/yr
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $764 | $605 |
$117
5,858
kWh
|
$647
-
kW-mo/yr
|
- | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $159,390 | $10,250 | - | - |
$4,140
-
MMBtu
|
$155,250 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,059 | $2,380 |
$261
13,140
kWh
|
$798
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,920 | $1,786 |
$473
23,814
kWh
|
$1,447
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $165,141 | $15,424 |
$1,278
64,268
kWh
|
$4,473
-
kW-mo/yr
|
$4,140
-
MMBtu
|
$155,250 | ||
TOTAL IMPLEMENTED | $5,170 | $5,011 |
$1,157
58,194
kWh
|
$4,013
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs