Assessment Year | 2002 |
---|---|
Principal Product | Corrugated Container |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $50 M to 100M |
# of Employees | 214 |
Plant Area |
291,350
ft2
|
Annual Production | 1,240,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $691,285 | 8,619,000 |
kWh
|
$0.080 |
Electricity Demand | $121,151 | 17,738 |
kW-mo/yr
|
$6.83 |
Natural Gas | $482,020 | 96,208 |
MMBtu
|
$5.01 |
Fuel Oil #2 | $126,936 | 20,564 |
MMBtu
|
$6.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,649 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4112: Install soft-start to eliminate nuisance trips | $20,390 | $42,000 | - |
$20,390
-
kW-mo/yr
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $18,173 | $10,000 | - |
$18,173
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,631 | $1,500 |
$3,502
53,066
kWh
|
$129
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $3,077 | $1,920 |
$2,270
34,396
kWh
|
$807
-
kW-mo/yr
|
- | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $12,299 | $750 | - | - |
$12,299
-
MMBtu
|
|
06 | 2.2414: Use waste heat from hot flue gases to preheat | $8,033 | $16,000 | - | - |
$8,033
-
MMBtu
|
|
07 | 2.4314: Use synthetic lubricant | $4,719 | $400 |
$3,803
57,619
kWh
|
$916
-
kW-mo/yr
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,628 | - |
$3,415
51,746
kWh
|
$1,213
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $74,950 | $72,570 |
$12,990
196,827
kWh
|
$41,628
-
kW-mo/yr
|
$20,332
-
MMBtu
|
||
TOTAL IMPLEMENTED | $20,649 | $2,650 |
$7,305
110,685
kWh
|
$1,045
-
kW-mo/yr
|
$12,299
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs