Assessment Year | 2002 |
---|---|
Principal Product | High Prssure Pipe Fittings |
NAICS |
n/a
|
SIC | 3462: Iron and Steel Forgings |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
60,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $149,073 | 1,564,505 |
kWh
|
$0.095 |
Electricity Demand | $93,288 | 13,470 |
kW-mo/yr
|
$6.93 |
Natural Gas | $73,646 | 10,531 |
MMBtu
|
$6.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $3,395 | $1,000 |
$2,284
63,970
kWh
|
$1,111
-
kW-mo/yr
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,492 | - |
$2,349
65,797
kWh
|
$1,143
-
kW-mo/yr
|
- | - | |
03 | 2.3212: Optimize plant power factor | $13,648 | $33,900 | - | - | $13,648 | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,017 | $100 |
$3,017
84,504
kWh
|
- | - | - | |
05 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $10,644 | $20,000 | - | - | - |
$10,644
-
MMBtu
|
|
TOTAL RECOMMENDED | $34,196 | $55,000 |
$7,650
214,271
kWh
|
$2,254
-
kW-mo/yr
|
$13,648 |
$10,644
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs