Assessment Year | 2002 |
---|---|
Principal Product | Power Transmission Equipment |
NAICS |
n/a
|
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
415,454
ft2
|
Annual Production | 33,000
ton
|
Production Hrs. Annual | 6,500
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $998,560 | 27,347,634 |
kWh
|
$0.037 |
Electricity Demand | $366,883 | 36,466 |
kW-mo/yr
|
$10.06 |
Natural Gas | $490,000 | 61,936 |
MMBtu
|
$7.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $142,585 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,714 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $54,428 | $30,000 | - | - |
$54,428
-
MMBtu
|
|
02 | 2.2414: Use waste heat from hot flue gases to preheat | $20,604 | $31,000 | - | - |
$20,604
-
MMBtu
|
|
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $43,767 | $25,000 | - |
$43,767
-
kW-mo/yr
|
- | |
04 | 2.2437: Recover waste heat from equipment | $14,099 | $11,750 | - | - |
$14,099
-
MMBtu
|
|
05 | 2.4221: Install compressor air intakes in coolest locations | $6,615 | $3,000 |
$2,569
101,539
kWh
|
$4,046
-
kW-mo/yr
|
- | |
06 | 2.4238: Do not use compressed air for personal cooling | $370 | $700 |
$112
4,421
kWh
|
$258
-
kW-mo/yr
|
- | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,702 | - |
$1,049
41,463
kWh
|
$1,653
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $142,585 | $101,450 |
$3,730
147,423
kWh
|
$49,724
-
kW-mo/yr
|
$89,131
-
MMBtu
|
||
TOTAL IMPLEMENTED | $20,714 | $14,750 |
$2,569
101,539
kWh
|
$4,046
-
kW-mo/yr
|
$14,099
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs