ITAC Assessment: HO0220
ITAC logo
ITAC Assessment: HO0220
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Telecommunication Eqpt.
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 95,000
ft2
Annual Production 1,400
pieces
Production Hrs. Annual 4,335
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,547 1,600,821
kWh
Electricity Demand $72,622 6,259
kW-mo/yr
Electricity Fees $4,710 -
Natural Gas $11,600 1,552
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,810 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,042 $21,460 $5,026
94,080
kWh
$3,016
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $2,415 $1,000 $2,415
45,135
kWh
- -
03 2.7124: Make a practice of turning off lights when not needed $449 $221 $449
8,499
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,118 $40 $1,326
24,912
kWh
$792
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,955 $600 $2,955
55,393
kWh
- -
06 2.6218: Turn off equipment when not in use $1,181 $120 $749
14,068
kWh
$432
-
kW-mo/yr
-
07 4.321: Optimize production lot sizes and inventories $7,650 $5,000 - - $7,650
TOTAL RECOMMENDED $24,810 $28,441 $12,920
242,087
kWh
$4,240
-
kW-mo/yr
$7,650
TOTAL IMPLEMENTED $7,000 $1,941 $6,568
123,095
kWh
$432
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs