| Assessment Year | 2000 |
|---|---|
| Principal Product | Telecommunication Eqpt. |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 140 |
| Plant Area |
95,000
ft2
|
| Annual Production | 1,400
pieces
|
| Production Hrs. Annual | 4,335
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $85,547 | 1,600,821 |
kWh
|
$0.053 |
| Electricity Demand | $72,622 | 6,259 |
kW-mo/yr
|
$11.60 |
| Electricity Fees | $4,710 | - |
|
- |
| Natural Gas | $11,600 | 1,552 |
MMBtu
|
$7.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,810 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,000 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,042 | $21,460 |
$5,026
94,080
kWh
|
$3,016
-
kW-mo/yr
|
- | |
| 02 | 2.7135: Install occupancy sensors | $2,415 | $1,000 |
$2,415
45,135
kWh
|
- | - | |
| 03 | 2.7124: Make a practice of turning off lights when not needed | $449 | $221 |
$449
8,499
kWh
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,118 | $40 |
$1,326
24,912
kWh
|
$792
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,955 | $600 |
$2,955
55,393
kWh
|
- | - | |
| 06 | 2.6218: Turn off equipment when not in use | $1,181 | $120 |
$749
14,068
kWh
|
$432
-
kW-mo/yr
|
- | |
| 07 | 4.321: Optimize production lot sizes and inventories | $7,650 | $5,000 | - | - | $7,650 | |
| TOTAL RECOMMENDED | $24,810 | $28,441 |
$12,920
242,087
kWh
|
$4,240
-
kW-mo/yr
|
$7,650 | ||
| TOTAL IMPLEMENTED | $7,000 | $1,941 |
$6,568
123,095
kWh
|
$432
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs