ITAC Assessment: LE0121
ITAC logo
ITAC Assessment: LE0121
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Laminated Industrial Favrics
NAICS
n/a
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 237,000
ft2
Annual Production 21,000
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $241,763 3,049,200
kWh
Electricity Demand $90,469 9,074
kW-mo/yr
Natural Gas $130,092 22,793
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,416 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,319

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $13,570 $2,500 - $13,570
-
kW-mo/yr
-
02 2.2123: Insulate feedwater tank $498 $260 - - $498
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $756 $1,000 - - $756
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $1,010 $1,280 $479
6,034
kWh
$531
-
kW-mo/yr
-
05 2.5195: Change product design to reduce energy requirements $14,087 $1,500 $11,074
139,651
kWh
$3,013
-
kW-mo/yr
-
06 2.6218: Turn off equipment when not in use $3,495 - $3,495
44,075
kWh
- -
TOTAL RECOMMENDED $33,416 $6,540 $15,048
189,760
kWh
$17,114
-
kW-mo/yr
$1,254
-
MMBtu
TOTAL IMPLEMENTED $18,319 $3,760 $3,495
44,075
kWh
$13,570
-
kW-mo/yr
$1,254
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs