ITAC Assessment: LE0119
ITAC logo
ITAC Assessment: LE0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Printed, Laminated Flexible Packging
NAICS
n/a
SIC 2671: Packaging Paper and Plastics Film, Coated and Laminated
Sales Range $10
M
to 50
M
# of Employees 147
Plant Area 110,000
ft2
Annual Production 4,800
lb
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $372,262 6,189,400
kWh
Natural Gas $279,898 44,152
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,078 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,581

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $4,354 $1,920 $4,354
72,570
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,434 - $4,434
73,903
kWh
-
03 2.7135: Install occupancy sensors $1,497 $1,250 $1,497
24,960
kWh
-
04 2.7496: Install partitions to reduce size of conditioned space $19,921 $1,000 - $19,921
-
MMBtu
05 2.2426: Use waste heat from flue gases to heat space conditioning air $17,872 $18,500 - $17,872
-
MMBtu
TOTAL RECOMMENDED $48,078 $22,670 $10,285
171,433
kWh
$37,793
-
MMBtu
TOTAL IMPLEMENTED $46,581 $21,420 $8,788
146,473
kWh
$37,793
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs