ITAC Assessment: LE0106
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Electronics
NAICS
n/a
SIC 3661: Telephone and Telegraph Apparatus
Sales Range $50
M
to 100
M
# of Employees 249
Plant Area 104,000
ft2
Annual Production 1,500
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $185,512 2,419,624
kWh
Electricity Demand $7,736 776
kW-mo/yr
Natural Gas $30,586 3,404
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,303 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,749

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 3.1162: Use less wasteful packaging $1,700 - - - - $1,700
-
lb
02 2.4221: Install compressor air intakes in coolest locations $561 $640 $423
6,048
kWh
$138
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,150 $4,410 $4,672
60,678
kWh
$1,478
-
kW-mo/yr
- -
04 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $9,638 - $9,638
125,174
kWh
- - -
05 2.7135: Install occupancy sensors $961 $1,250 $961
12,480
kWh
- - -
06 2.7233: Use properly designed and sized hvac equipment $6,293 $41,225 - - $6,293
-
MMBtu
-
TOTAL RECOMMENDED $25,303 $47,525 $15,694
204,380
kWh
$1,616
-
kW-mo/yr
$6,293
-
MMBtu
$1,700
-
lb
TOTAL IMPLEMENTED $16,749 $5,660 $15,271
198,332
kWh
$1,478
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs