| Assessment Year | 2000 |
|---|---|
| Principal Product | electrical metering equipment |
| NAICS |
n/a
|
| SIC | 3825: Instruments for Measuring and Testing of Electricity and Electrical Signals |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
108,800
ft2
|
| Annual Production | 432,000
units
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $123,116 | 2,810,906 |
kWh
|
$0.044 |
| Electricity Demand | $35,839 | 8,299 |
kW-mo/yr
|
$4.32 |
| Electricity Fees | $23,433 | - |
|
- |
| Natural Gas | $81,214 | 14,516 |
MMBtu
|
$5.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,135 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $13,917 | - | n/a | - | - | - | - | - | $13,917 | - |
| 02 | 2.4226: Use / purchase optimum sized compressor | $6,154 | $11,500 | n/a |
$4,211
107,562
kWh
|
$1,943
-
kW-mo/yr
|
- | - | - | - | - |
| 03 | 2.2437: Recover waste heat from equipment | $3,963 | $1,505 | n/a | - | - |
$3,963
-
MMBtu
|
- | - | - | - |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,604 | $40 | n/a |
$1,496
38,101
kWh
|
$1,108
-
kW-mo/yr
|
- | - | - | - | - |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,422 | $1,050 | n/a |
$1,284
32,532
kWh
|
$1,138
-
kW-mo/yr
|
- | - | - | - | - |
| 06 | 3.4151: Minimize water usage | $4,075 | $4,075 | n/a | - | - |
$2,845
-
MMBtu
|
$1,698
-
Tgal
|
$(-2,400.0) | - |
$1,932
-
Tgal
|
| TOTAL RECOMMENDED | $33,135 | $18,170 |
$6,991
178,195
kWh
|
$4,189
-
kW-mo/yr
|
$6,808
-
MMBtu
|
$1,698
-
Tgal
|
$(-2,400.0) | $13,917 |
$1,932
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs