Assessment Year | 2000 |
---|---|
Principal Product | fossil fuel burners |
NAICS |
n/a
|
SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
149,000
ft2
|
Annual Production | 6,016
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $84,778 | 2,032,532 |
kWh
|
$0.042 |
Electricity Demand | $23,677 | 6,607 |
kW-mo/yr
|
$3.58 |
Natural Gas | $22,121 | 4,100 |
MMBtu
|
$5.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $970 | $1,480 |
$760
18,757
kWh
|
$50
-
kW-mo/yr
|
$160 | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $580 | - |
$580
14,361
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $400 | $200 |
$320
7,913
kWh
|
$80
-
kW-mo/yr
|
- | - | - | |
04 | 3.4155: Meter waste water | $2,980 | $1,910 | - | - | - | $2,980 | - | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $1,180 | $1,740 | - | - | - | - |
$1,180
-
Tgal
|
|
TOTAL RECOMMENDED | $6,110 | $5,330 |
$1,660
41,031
kWh
|
$130
-
kW-mo/yr
|
$160 | $2,980 |
$1,180
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs