ITAC Assessment: KU0537
ITAC logo
ITAC Assessment: KU0537
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product fossil fuel burners
NAICS
n/a
SIC 3433: Heating Equipment, Except Electric and Warm Air Furnaces
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 149,000
ft2
Annual Production 6,016
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,778 2,032,532
kWh
Electricity Demand $23,677 6,607
kW-mo/yr
Natural Gas $22,121 4,100
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,110 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $970 $1,480 $760
18,757
kWh
$50
-
kW-mo/yr
$160 - -
02 2.4226: Use / purchase optimum sized compressor $580 - $580
14,361
kWh
- - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $400 $200 $320
7,913
kWh
$80
-
kW-mo/yr
- - -
04 3.4155: Meter waste water $2,980 $1,910 - - - $2,980 -
05 3.4111: Use closed cycle process to minimize waste water production $1,180 $1,740 - - - - $1,180
-
Tgal
TOTAL RECOMMENDED $6,110 $5,330 $1,660
41,031
kWh
$130
-
kW-mo/yr
$160 $2,980 $1,180
-
Tgal
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs