Assessment Year | 1999 |
---|---|
Principal Product | audiocassettes |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 165 |
Plant Area |
92,000
ft2
|
Annual Production | 11,700,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $213,384 | 13,156,507 |
kWh
|
$0.016 |
Electricity Demand | $241,081 | 21,474 |
kW-mo/yr
|
$11.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $105,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $8,350 | $9,600 | - | - | - | - | $8,350 | - | |
02 | 2.4314: Use synthetic lubricant | $2,350 | $3,690 |
$870
56,272
kWh
|
$850
-
kW-mo/yr
|
- | - | - | $630 | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,520 | $2,670 |
$770
49,531
kWh
|
$750
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,370 | $110 |
$690
44,549
kWh
|
$680
-
kW-mo/yr
|
- | - | - | - | |
05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $600 | - | - | - |
$600
-
lb
|
- | - | - | |
06 | 4.441: Install automatic packing equipment | $91,030 | $325,000 |
$(-1,680.0)
(-108,734)
kWh
|
$(-1,640.0)
-
kW-mo/yr
|
- | $94,350 | - | - | |
TOTAL RECOMMENDED | $105,220 | $341,070 |
$650
41,618
kWh
|
$640
-
kW-mo/yr
|
$600
-
lb
|
$94,350 | $8,350 | $630 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs