ITAC Assessment: KU0531
ITAC logo
ITAC Assessment: KU0531
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product audiocassettes
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 165
Plant Area 92,000
ft2
Annual Production 11,700,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,384 13,156,507
kWh
Electricity Demand $241,081 21,474
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $105,220 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $8,350 $9,600 - - - - $8,350 -
02 2.4314: Use synthetic lubricant $2,350 $3,690 $870
56,272
kWh
$850
-
kW-mo/yr
- - - $630
03 2.4221: Install compressor air intakes in coolest locations $1,520 $2,670 $770
49,531
kWh
$750
-
kW-mo/yr
- - - -
04 2.7111: Reduce illumination to minimum necessary levels $1,370 $110 $690
44,549
kWh
$680
-
kW-mo/yr
- - - -
05 3.5212: Regrind, reuse, or sell scrap plastic parts $600 - - - $600
-
lb
- - -
06 4.441: Install automatic packing equipment $91,030 $325,000 $(-1,680.0)
(-108,734)
kWh
$(-1,640.0)
-
kW-mo/yr
- $94,350 - -
TOTAL RECOMMENDED $105,220 $341,070 $650
41,618
kWh
$640
-
kW-mo/yr
$600
-
lb
$94,350 $8,350 $630
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs