Assessment Year | 1999 |
---|---|
Principal Product | bulkheads, ramps,closures |
NAICS |
n/a
|
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $10 M to 50M |
# of Employees | 102 |
Plant Area |
55,000
ft2
|
Annual Production | 22,000
pieces
|
Production Hrs. Annual | 3,510
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $32,166 | 634,232 |
kWh
|
$0.051 |
Electricity Demand | $5,247 | 2,114 |
kW-mo/yr
|
$2.48 |
Natural Gas | $17,844 | 3,125 |
MMBtu
|
$5.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $660 | $190 |
$460
10,258
kWh
|
$200
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $600 | $930 |
$170
3,810
kWh
|
$30
-
kW-mo/yr
|
$400 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $360 | $700 |
$250
5,569
kWh
|
$110
-
kW-mo/yr
|
- | - | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $4,840 | $840 | - | - | - | $4,840 | |
TOTAL RECOMMENDED | $6,460 | $2,660 |
$880
19,637
kWh
|
$340
-
kW-mo/yr
|
$400 | $4,840 | ||
TOTAL IMPLEMENTED | $5,800 | $2,470 |
$420
9,379
kWh
|
$140
-
kW-mo/yr
|
$400 | $4,840 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs