ITAC Assessment: KU0529
ITAC logo
ITAC Assessment: KU0529
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product bulkheads, ramps,closures
NAICS
n/a
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 102
Plant Area 55,000
ft2
Annual Production 22,000
pieces
Production Hrs. Annual 3,510
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,166 634,232
kWh
Electricity Demand $5,247 2,114
kW-mo/yr
Natural Gas $17,844 3,125
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,460 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,800

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $660 $190 $460
10,258
kWh
$200
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $600 $930 $170
3,810
kWh
$30
-
kW-mo/yr
$400 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $360 $700 $250
5,569
kWh
$110
-
kW-mo/yr
- -
04 3.2123: Convert to high volume low pressure (hvlp) paint guns $4,840 $840 - - - $4,840
TOTAL RECOMMENDED $6,460 $2,660 $880
19,637
kWh
$340
-
kW-mo/yr
$400 $4,840
TOTAL IMPLEMENTED $5,800 $2,470 $420
9,379
kWh
$140
-
kW-mo/yr
$400 $4,840
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs