Assessment Year | 1999 |
---|---|
Principal Product | dried soy, rice & milk products |
NAICS |
n/a
|
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $1 M to 5M |
# of Employees | 37 |
Plant Area |
77,570
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $205,410 | 4,551,876 |
kWh
|
$0.045 |
Electricity Demand | $106,357 | 13,664 |
kW-mo/yr
|
$7.78 |
Natural Gas | $330,180 | 109,368 |
MMBtu
|
$3.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,520 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,520 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $9,520 | $18,350 | - | - |
$9,520
-
MMBtu
|
- | - | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,110 | $2,500 | - | - |
$9,110
-
MMBtu
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,820 | $3,790 |
$1,210
27,550
kWh
|
$400
-
kW-mo/yr
|
- | $1,210 | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,070 | $1,270 |
$680
15,533
kWh
|
$390
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2511: Insulate bare equipment | $750 | $680 | - | - |
$750
-
MMBtu
|
- | - | - | |
06 | 2.4314: Use synthetic lubricant | $650 | $1,160 |
$370
8,206
kWh
|
$210
-
kW-mo/yr
|
- | - | - | $70 | |
07 | 2.8114: Change rate schedules or other changes in utility service | $600 | - | - | - | - | - | $600 | - | |
TOTAL RECOMMENDED | $24,520 | $27,750 |
$2,260
51,289
kWh
|
$1,000
-
kW-mo/yr
|
$19,380
-
MMBtu
|
$1,210 | $600 | $70 | ||
TOTAL IMPLEMENTED | $24,520 | $27,750 |
$2,260
51,289
kWh
|
$1,000
-
kW-mo/yr
|
$19,380
-
MMBtu
|
$1,210 | $600 | $70 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs