ITAC Assessment: KU0524
ITAC logo
ITAC Assessment: KU0524
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product dried soy, rice & milk products
NAICS
n/a
SIC 2023: Dry, Condensed, and Evaporated Dairy Products
Sales Range $1
M
to 5
M
# of Employees 37
Plant Area 77,570
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $205,410 4,551,876
kWh
Electricity Demand $106,357 13,664
kW-mo/yr
Natural Gas $330,180 109,368
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,520 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,520

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1243: Use heat from boiler blowdown to preheat boiler feed water $9,520 $18,350 - - $9,520
-
MMBtu
- - -
02 2.1233: Analyze flue gas for proper air/fuel ratio $9,110 $2,500 - - $9,110
-
MMBtu
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,820 $3,790 $1,210
27,550
kWh
$400
-
kW-mo/yr
- $1,210 - -
04 2.4221: Install compressor air intakes in coolest locations $1,070 $1,270 $680
15,533
kWh
$390
-
kW-mo/yr
- - - -
05 2.2511: Insulate bare equipment $750 $680 - - $750
-
MMBtu
- - -
06 2.4314: Use synthetic lubricant $650 $1,160 $370
8,206
kWh
$210
-
kW-mo/yr
- - - $70
07 2.8114: Change rate schedules or other changes in utility service $600 - - - - - $600 -
TOTAL RECOMMENDED $24,520 $27,750 $2,260
51,289
kWh
$1,000
-
kW-mo/yr
$19,380
-
MMBtu
$1,210 $600 $70
TOTAL IMPLEMENTED $24,520 $27,750 $2,260
51,289
kWh
$1,000
-
kW-mo/yr
$19,380
-
MMBtu
$1,210 $600 $70
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs