ITAC Assessment: KU0514
ITAC logo
ITAC Assessment: KU0514
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product carbonated beverages
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 115
Plant Area 216,000
ft2
Annual Production 36,000,000
pieces
Production Hrs. Annual 4,964
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $407,016 7,369,578
kWh
Electricity Demand $92,379 17,759
kW-mo/yr
Natural Gas $161,592 40,840
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $158,630 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $147,970

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.2211: Use optimum temperature $25,150 $9,360 - - $25,150
-
MMBtu
- - -
02 2.1243: Use heat from boiler blowdown to preheat boiler feed water $4,760 $13,490 - - $4,760
-
MMBtu
- - -
03 2.7291: Reschedule and rearrange multiple-source heating systems $2,250 $280 - - $2,250
-
MMBtu
- - -
04 2.4221: Install compressor air intakes in coolest locations $1,950 $3,040 $1,070
35,463
kWh
$880
-
kW-mo/yr
- - - -
05 2.2437: Recover waste heat from equipment $1,300 $1,960 - - $1,300
-
MMBtu
- - -
06 2.2511: Insulate bare equipment $1,120 $860 - $500
-
kW-mo/yr
$620
-
MMBtu
- - -
07 3.4151: Minimize water usage $12,240 $22,300 - - - $12,240
-
Tgal
- -
08 3.5217: Reuse / recycle/ sell paper products $2,650 $480 - - - - $2,650
-
lb
-
09 3.4154: Eliminate leaks in water lines and valves $490 $260 - - - $490
-
Tgal
- -
10 4.111: Add equipment/ operators to reduce production bottleneck $106,720 $288,000 - - - - - $106,720
TOTAL RECOMMENDED $158,630 $340,030 $1,070
35,463
kWh
$1,380
-
kW-mo/yr
$34,080
-
MMBtu
$12,730
-
Tgal
$2,650
-
lb
$106,720
TOTAL IMPLEMENTED $147,970 $321,060 - $500
-
kW-mo/yr
$28,020
-
MMBtu
$12,730
-
Tgal
- $106,720
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs