Assessment Year | 1998 |
---|---|
Principal Product | rubber belting |
NAICS |
n/a
|
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
59,300
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,086 | 1,043,963 |
kWh
|
$0.057 |
Electricity Demand | $26,483 | 4,185 |
kW-mo/yr
|
$6.33 |
Natural Gas | $72,595 | 15,382 |
MMBtu
|
$4.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,600 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,870 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,100 | $9,690 |
$3,290
58,324
kWh
|
$810
-
kW-mo/yr
|
- | - | |
02 | 2.2511: Insulate bare equipment | $900 | $1,190 | - | - |
$900
-
MMBtu
|
- | |
03 | 2.4226: Use / purchase optimum sized compressor | $870 | $7,500 |
$640
11,430
kWh
|
$230
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $540 | $430 |
$360
6,448
kWh
|
$180
-
kW-mo/yr
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $520 | $890 |
$370
6,741
kWh
|
$150
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $320 | $200 |
$320
5,862
kWh
|
- | - | - | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $22,350 | $790 |
$(-1,820.0)
(-32,239)
kWh
|
$(-30.0)
-
kW-mo/yr
|
- |
$24,200
-
Tgal
|
|
TOTAL RECOMMENDED | $29,600 | $20,690 |
$3,160
56,566
kWh
|
$1,340
-
kW-mo/yr
|
$900
-
MMBtu
|
$24,200
-
Tgal
|
||
TOTAL IMPLEMENTED | $27,870 | $12,560 |
$1,840
32,826
kWh
|
$930
-
kW-mo/yr
|
$900
-
MMBtu
|
$24,200
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs