ITAC Assessment: KU0507
ITAC logo
ITAC Assessment: KU0507
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product rubber belting
NAICS
n/a
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $10
M
to 50
M
# of Employees 54
Plant Area 59,300
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,086 1,043,963
kWh
Electricity Demand $26,483 4,185
kW-mo/yr
Natural Gas $72,595 15,382
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,600 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,870

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,100 $9,690 $3,290
58,324
kWh
$810
-
kW-mo/yr
- -
02 2.2511: Insulate bare equipment $900 $1,190 - - $900
-
MMBtu
-
03 2.4226: Use / purchase optimum sized compressor $870 $7,500 $640
11,430
kWh
$230
-
kW-mo/yr
- -
04 2.4221: Install compressor air intakes in coolest locations $540 $430 $360
6,448
kWh
$180
-
kW-mo/yr
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $520 $890 $370
6,741
kWh
$150
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $320 $200 $320
5,862
kWh
- - -
07 3.4111: Use closed cycle process to minimize waste water production $22,350 $790 $(-1,820.0)
(-32,239)
kWh
$(-30.0)
-
kW-mo/yr
- $24,200
-
Tgal
TOTAL RECOMMENDED $29,600 $20,690 $3,160
56,566
kWh
$1,340
-
kW-mo/yr
$900
-
MMBtu
$24,200
-
Tgal
TOTAL IMPLEMENTED $27,870 $12,560 $1,840
32,826
kWh
$930
-
kW-mo/yr
$900
-
MMBtu
$24,200
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs