ITAC Assessment: KU0504
ITAC logo
ITAC Assessment: KU0504
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product custom plastic extursions
NAICS
n/a
SIC 3082: Unsupported Plastics Profile Shapes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 135,000
ft2
Annual Production 7,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,062 3,601,700
kWh
Electricity Demand $40,584 7,743
kW-mo/yr
Natural Gas $8,003 1,483
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,020

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
01 2.4239: Eliminate or reduce compressed air usage $14,180 $10,050 $8,600
464,537
kWh
$5,580
-
kW-mo/yr
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,210 $4,420 $1,340
72,685
kWh
$870
-
kW-mo/yr
- - - -
03 2.4221: Install compressor air intakes in coolest locations $1,240 $390 $750
40,739
kWh
$490
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $840 $350 $510
27,550
kWh
$330
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $450 $1,020 $220
12,016
kWh
$150
-
kW-mo/yr
- $80 - -
06 3.5311: Recover and reuse waste material $22,040 $570 - - $22,040
-
lb
- - -
07 4.445: Install equipment to move product $43,400 $82,500 $(-1,150.0)
(-62,427)
kWh
$(-2,250.0)
-
kW-mo/yr
- $46,800 - -
08 4.125: $8,520 $8,480 - - - - - $8,520
09 4.131: Modify process to reduce material use/cost $6,820 $18,750 - - - - $6,820 -
TOTAL RECOMMENDED $99,700 $126,530 $10,270
555,100
kWh
$5,170
-
kW-mo/yr
$22,040
-
lb
$46,880 $6,820 $8,520
TOTAL IMPLEMENTED $33,020 $43,070 $10,670
576,788
kWh
$6,930
-
kW-mo/yr
- $80 $6,820 $8,520
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs