| Assessment Year | 1998 |
|---|---|
| Principal Product | hydraulic/pneumatic jacks |
| NAICS |
n/a
|
| SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
| Sales Range | $10 M to 50M |
| # of Employees | 175 |
| Plant Area |
146,400
ft2
|
| Annual Production | 16,655
pieces
|
| Production Hrs. Annual | 4,100
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $81,344 | 1,912,954 |
kWh
|
$0.043 |
| Electricity Demand | $23,716 | 6,300 |
kW-mo/yr
|
$3.76 |
| Natural Gas | $59,292 | 10,883 |
MMBtu
|
$5.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $97,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,360 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,610 | $1,000 | - | - |
$1,610
-
MMBtu
|
- | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $760 | $2,630 |
$600
14,068
kWh
|
$160
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $640 | $780 |
$190
4,396
kWh
|
$20
-
kW-mo/yr
|
- | - | $430 | - | - | |
| 04 | 2.7132: Install timers on light switches in little used areas | $590 | $800 |
$590
13,775
kWh
|
- | - | - | - | - | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $420 | $690 | - | - |
$420
-
MMBtu
|
- | - | - | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $370 | $1,140 |
$660
15,533
kWh
|
$60
-
kW-mo/yr
|
$(-350.0)
-
MMBtu
|
- | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $240 | $210 |
$190
4,396
kWh
|
$50
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,650 | $7,000 | - | - | - |
$2,890
-
lb
|
$(-240.0) | - | - | |
| 09 | 3.5316: Contract a wood pallet recycling company | $1,560 | - | - | - | - |
$1,560
-
lb
|
- | - | - | |
| 10 | 4.652: Replace existing equipment with more suitable substitutes | $54,580 | $150,500 |
$(-430.0)
(-10,258)
kWh
|
$(-110.0)
-
kW-mo/yr
|
- | - | $38,500 | $16,620 | - | |
| 11 | 4.652: Replace existing equipment with more suitable substitutes | $34,550 | $60,000 | - | - | - | - | $24,000 | - | $10,550 | |
| TOTAL RECOMMENDED | $97,970 | $224,750 |
$1,800
41,910
kWh
|
$180
-
kW-mo/yr
|
$1,680
-
MMBtu
|
$4,450
-
lb
|
$62,690 | $16,620 | $10,550 | ||
| TOTAL IMPLEMENTED | $39,360 | $64,620 |
$980
22,860
kWh
|
$230
-
kW-mo/yr
|
$1,610
-
MMBtu
|
$1,560
-
lb
|
$24,430 | - | $10,550 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs