ITAC Assessment: KU0479
ITAC logo
ITAC Assessment: KU0479
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product grain bins
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 396,000
ft2
Annual Production 2,650
pieces
Production Hrs. Annual 4,051
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $237,161 4,592,614
kWh
Electricity Demand $64,912 16,920
kW-mo/yr
Natural Gas $177,363 42,351
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $279,364 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $93,510

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,560 $2,610 $8,650
167,644
kWh
$1,910
-
kW-mo/yr
- - - - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,030 $19,320 $3,850
74,736
kWh
$1,180
-
kW-mo/yr
- - - - - - -
03 2.4221: Install compressor air intakes in coolest locations $3,100 $320 $2,540
49,238
kWh
$560
-
kW-mo/yr
- - - - - - -
04 2.4314: Use synthetic lubricant $2,330 $3,220 $1,590
30,774
kWh
$350
-
kW-mo/yr
- - - - - - $390
05 2.7135: Install occupancy sensors $590 $450 $590
11,430
kWh
- - - - - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $540 $780 $220
4,396
kWh
$20
-
kW-mo/yr
- - - - - $300 -
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $59,380 $1,160 - - - - $18,810
-
gal
- - - $40,570
08 3.8113: Prevent excessive solvent usage (operator training) $8,940 $800 - - - - - - $2,200
-
lb
$370 $6,370
09 3.8132: Use less toxic and volatile solvent substitutes $4,120 $2,990 $(-270.0)
(-5,275)
kWh
$(-60.0)
-
kW-mo/yr
- - - $3,170
-
gal
- - $1,280
10 4.425: Eliminate/reduce redundant inspections $165,324 $188,280 $230
4,689
kWh
- $19,930
-
MMBtu
$744
-
Tgal
- - - $144,420 -
11 4.452: Eliminate shift $19,450 $16,980 - - - - - - - $53,200 $(-33,750.0)
TOTAL RECOMMENDED $279,364 $236,910 $17,400
337,632
kWh
$3,960
-
kW-mo/yr
$19,930
-
MMBtu
$744
-
Tgal
$18,810
-
gal
$3,170
-
gal
$2,200
-
lb
$198,290 $14,860
TOTAL IMPLEMENTED $93,510 $23,740 $8,380
162,369
kWh
$1,850
-
kW-mo/yr
- - $18,810
-
gal
$3,170
-
gal
- $53,200 $8,100
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs