Assessment Year | 1997 |
---|---|
Principal Product | printed products/catalogs |
NAICS |
n/a
|
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 109 |
Plant Area |
65,000
ft2
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,376 | 1,133,939 |
kWh
|
$0.023 |
Electricity Demand | $48,924 | 5,472 |
kW-mo/yr
|
$8.94 |
Natural Gas | $64,827 | 14,958 |
MMBtu
|
$4.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,280 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,350 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $15,110 | $58,000 | - | - |
$15,110
-
MMBtu
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,330 | $330 |
$570
27,843
kWh
|
$760
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4323: Use optimum size and capacity equipment | $1,130 | - |
$1,130
56,272
kWh
|
- | - | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $730 | $170 |
$320
15,826
kWh
|
$410
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $500 | $780 |
$90
4,396
kWh
|
$50
-
kW-mo/yr
|
- | - | $360 | - | |
06 | 2.4133: Use most efficient type of electric motors | $290 | $1,050 |
$120
6,155
kWh
|
$170
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $190 | $400 |
$190
9,672
kWh
|
- | - | - | - | - | |
08 | 3.5121: Recycle waste ink and cleanup solvent | $3,000 | - | - | - | - |
$1,920
-
lb
|
- | $1,080 | |
TOTAL RECOMMENDED | $22,280 | $60,730 |
$2,420
120,164
kWh
|
$1,390
-
kW-mo/yr
|
$15,110
-
MMBtu
|
$1,920
-
lb
|
$360 | $1,080 | ||
TOTAL IMPLEMENTED | $5,350 | $1,550 |
$1,010
49,824
kWh
|
$1,340
-
kW-mo/yr
|
- |
$1,920
-
lb
|
- | $1,080 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs