ITAC Assessment: KU0469
ITAC logo
ITAC Assessment: KU0469
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product gray and ductile iron castings
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $5
M
to 10
M
# of Employees 125
Plant Area 102,000
ft2
Annual Production 3,500
ton
Production Hrs. Annual 6,000
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $426,247 12,315,651
kWh
Electricity Demand $62,356 4,877
kW-mo/yr
Natural Gas $35,878 11,385
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,445 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,498

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
01 3.2124: Convert to air assisted / airless paint guns $19,601 $1,200 - - - - $19,601
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,110 $376 $10,463
302,462
kWh
$647
-
kW-mo/yr
- - -
03 2.4133: Use most efficient type of electric motors $5,246 $15,818 $4,932
142,438
kWh
$314
-
kW-mo/yr
- - -
04 2.4221: Install compressor air intakes in coolest locations $4,608 $583 $4,217
121,923
kWh
$391
-
kW-mo/yr
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,808 $440 $1,696
48,945
kWh
$112
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $1,531 $850 $1,432
41,325
kWh
$99
-
kW-mo/yr
- - -
07 2.1133: Adjust burners for efficient operation $1,026 $1,000 - - $1,026
-
MMBtu
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $515 $660 $127
3,517
kWh
$5
-
kW-mo/yr
- $383 -
TOTAL RECOMMENDED $45,445 $20,927 $22,867
660,610
kWh
$1,568
-
kW-mo/yr
$1,026
-
MMBtu
$383 $19,601
TOTAL IMPLEMENTED $37,498 $19,054 $15,522
448,417
kWh
$966
-
kW-mo/yr
$1,026
-
MMBtu
$383 $19,601
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs