| Assessment Year | 1996 |
|---|---|
| Principal Product | portland cement |
| NAICS |
n/a
|
| SIC | 3241: Cement, Hydraulic |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
n/a
|
| Annual Production | 400,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,214,012 | 51,350,821 |
kWh
|
$0.024 |
| Electricity Demand | $1,149,100 | 79,873 |
kW-mo/yr
|
$14.39 |
| Natural Gas | $41,934 | 7,123 |
MMBtu
|
$5.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $900,168 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $899,394 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $785,416 | $3,675,000 |
$546,100
21,505,862
kWh
|
$423,066
-
kW-mo/yr
|
$(-183,750.0) | |
| 02 | 2.4133: Use most efficient type of electric motors | $65,015 | $163,148 |
$40,111
1,579,719
kWh
|
$24,904
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $27,993 | $10,657 |
$15,761
620,750
kWh
|
$12,232
-
kW-mo/yr
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $17,327 | $3,877 |
$9,756
384,232
kWh
|
$7,571
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,643 | $9,918 |
$2,051
80,891
kWh
|
$1,592
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $774 | $1,911 |
$436
17,292
kWh
|
$338
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $900,168 | $3,864,511 |
$614,215
24,188,746
kWh
|
$469,703
-
kW-mo/yr
|
$(-183,750.0) | ||
| TOTAL IMPLEMENTED | $899,394 | $3,862,600 |
$613,779
24,171,454
kWh
|
$469,365
-
kW-mo/yr
|
$(-183,750.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs