ITAC Assessment: KU0463
ITAC logo
ITAC Assessment: KU0463
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product new and rebuilt diesel engines
NAICS
n/a
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 67,000
ft2
Annual Production 5,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,192 2,536,049
kWh
Electricity Demand $17,716 4,608
kW-mo/yr
Natural Gas $59,840 13,046
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,153 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,051

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 3.3128: Utilize other methods to remove contaminants $24,383 $3,800 - - - $24,383
-
gal
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,482 $284 $1,924
72,685
kWh
$558
-
kW-mo/yr
- -
03 2.7135: Install occupancy sensors $1,237 $1,200 $875
33,118
kWh
$362
-
kW-mo/yr
- -
04 2.4133: Use most efficient type of electric motors $936 $2,112 $712
26,964
kWh
$224
-
kW-mo/yr
- -
05 2.1133: Adjust burners for efficient operation $633 $1,000 - - $633
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $482 $375 $374
14,068
kWh
$108
-
kW-mo/yr
- -
TOTAL RECOMMENDED $30,153 $8,771 $3,885
146,835
kWh
$1,252
-
kW-mo/yr
$633
-
MMBtu
$24,383
-
gal
TOTAL IMPLEMENTED $4,051 $3,396 $2,636
99,649
kWh
$782
-
kW-mo/yr
$633
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs