Assessment Year | 1994 |
---|---|
Principal Product | diesel generators |
NAICS |
n/a
|
SIC | 3621: Motors and Generators |
Sales Range | $5 M to 10M |
# of Employees | 430 |
Plant Area |
160,125
ft2
|
Annual Production | 5,500
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $169,404 | 2,418,816 |
kWh
|
$0.070 |
Natural Gas | $58,833 | 11,410 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,124 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 3.2121: Convert to electrostatic powder coating | $38,324 | $12,000 |
$6,734
96,131
kWh
|
- | $31,590 | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $18,466 | $2,616 |
$26,216
374,267
kWh
|
$(-7,750.0)
-
MMBtu
|
- | |
03 | 2.6218: Turn off equipment when not in use | $1,601 | $1,600 |
$1,601
22,860
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,291 | $300 |
$4,291
61,254
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,038 | $10 |
$3,038
43,376
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,279 | $240 |
$2,279
32,532
kWh
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $801 | $150 |
$801
11,430
kWh
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $965 | $1,197 |
$965
13,775
kWh
|
- | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $698 | $191 |
$698
9,965
kWh
|
- | - | |
10 | 2.6121: Reduce hot water temperature to the minimum required | $504 | $10 |
$287
4,103
kWh
|
$217
-
MMBtu
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,584 | $12,960 |
$5,584
58,617
kWh
|
- | - | |
12 | 2.7145: Install skylights | $3,223 | $4,920 |
$3,223
46,014
kWh
|
- | - | |
13 | 2.7135: Install occupancy sensors | $1,170 | $1,540 |
$1,170
16,706
kWh
|
- | - | |
14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $410 | $540 |
$410
2,931
kWh
|
- | - | |
TOTAL RECOMMENDED | $81,354 | $38,274 |
$57,297
793,961
kWh
|
$(-7,533.0)
-
MMBtu
|
$31,590 | ||
TOTAL IMPLEMENTED | $19,124 | $21,898 |
$18,907
245,897
kWh
|
$217
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs