ITAC Assessment: KU0446
ITAC logo
ITAC Assessment: KU0446
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product diesel generators
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $5
M
to 10
M
# of Employees 430
Plant Area 160,125
ft2
Annual Production 5,500
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $169,404 2,418,816
kWh
Natural Gas $58,833 11,410
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $81,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,124

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings
01 3.2121: Convert to electrostatic powder coating $38,324 $12,000 $6,734
96,131
kWh
- $31,590
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $18,466 $2,616 $26,216
374,267
kWh
$(-7,750.0)
-
MMBtu
-
03 2.6218: Turn off equipment when not in use $1,601 $1,600 $1,601
22,860
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,291 $300 $4,291
61,254
kWh
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $3,038 $10 $3,038
43,376
kWh
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $2,279 $240 $2,279
32,532
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $801 $150 $801
11,430
kWh
- -
08 2.4133: Use most efficient type of electric motors $965 $1,197 $965
13,775
kWh
- -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $698 $191 $698
9,965
kWh
- -
10 2.6121: Reduce hot water temperature to the minimum required $504 $10 $287
4,103
kWh
$217
-
MMBtu
-
11 2.7142: Utilize higher efficiency lamps and/or ballasts $5,584 $12,960 $5,584
58,617
kWh
- -
12 2.7145: Install skylights $3,223 $4,920 $3,223
46,014
kWh
- -
13 2.7135: Install occupancy sensors $1,170 $1,540 $1,170
16,706
kWh
- -
14 2.7142: Utilize higher efficiency lamps and/or ballasts $410 $540 $410
2,931
kWh
- -
TOTAL RECOMMENDED $81,354 $38,274 $57,297
793,961
kWh
$(-7,533.0)
-
MMBtu
$31,590
TOTAL IMPLEMENTED $19,124 $21,898 $18,907
245,897
kWh
$217
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs