Assessment Year | 1994 |
---|---|
Principal Product | Buses |
NAICS |
n/a
|
SIC | 3713: Truck and Bus Bodies |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
93,346
ft2
|
Annual Production | 1,300
pieces
|
Production Hrs. Annual | 2,535
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,246 | 954,279 |
kWh
|
$0.060 |
Natural Gas | $37,909 | 16,236 |
MMBtu
|
$2.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,188 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,880 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $4,336 | $1,050 |
$1,705
28,429
kWh
|
$2,631
-
MMBtu
|
- | |
02 | 2.2437: Recover waste heat from equipment | $7,231 | $37,260 |
$(-1,406.0)
(-23,447)
kWh
|
$8,637
-
MMBtu
|
- | |
03 | 3.4151: Minimize water usage | $11,654 | $7,175 | - | - | $11,654 | |
04 | 2.7145: Install skylights | $8,263 | $29,640 |
$8,263
137,749
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,920 | $4,726 |
$1,920
19,343
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,580 | $879 |
$1,580
17,292
kWh
|
- | - | |
07 | 2.7135: Install occupancy sensors | $756 | $1,550 |
$756
12,603
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $879 | $1,800 |
$879
14,068
kWh
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $756 | $2,793 |
$756
12,603
kWh
|
- | - | |
10 | 2.7132: Install timers on light switches in little used areas | $721 | $170 |
$721
12,016
kWh
|
- | - | |
11 | 2.2437: Recover waste heat from equipment | $282 | $1,420 | - |
$282
-
MMBtu
|
- | |
12 | 2.4314: Use synthetic lubricant | $440 | $1,395 |
$440
7,327
kWh
|
- | - | |
13 | 2.7447: Install vinyl strip / high speed / air curtain doors | $370 | $1,386 | - |
$370
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $39,188 | $91,244 |
$15,614
237,983
kWh
|
$11,920
-
MMBtu
|
$11,654 | ||
TOTAL IMPLEMENTED | $17,880 | $18,929 |
$5,856
75,322
kWh
|
$370
-
MMBtu
|
$11,654 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs