ITAC Assessment: OK1029
ITAC logo
ITAC Assessment: OK1029
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Wire harnesses
NAICS 335931: Current-Carrying Wiring Device Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $50
M
to 100
M
# of Employees 185
Plant Area 112,500
ft2
Annual Production 39,000
units
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,334 1,583,338
kWh
Electricity Demand $36,950 3,278
kW-mo/yr
Electricity Fees $11,755 -
Waste Disposal Costs
Water Usage $3,011 833
Tgal
TOTAL YEARLY COSTS $115,050
RECOMMENDED SAVINGS* $18,507 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,449

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,568 $2,250 $1,568
39,201
kWh
-
02 2.6218: Turn off equipment when not in use $4,512 - $4,512
112,795
kWh
-
03 2.7232: Replace existing hvac unit with high efficiency model $4,684 $22,100 $2,227
55,679
kWh
$2,457
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,197 $30,672 $4,086
102,155
kWh
$3,111
-
kW-mo/yr
05 2.6218: Turn off equipment when not in use $546 $522 $546
13,650
kWh
-
TOTAL RECOMMENDED $18,507 $55,544 $12,939
323,480
kWh
$5,568
-
kW-mo/yr
TOTAL IMPLEMENTED $13,449 $55,022 $7,881
197,035
kWh
$5,568
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs