ITAC Assessment: DS0080
ITAC logo
ITAC Assessment: DS0080
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Printed Paper Boxes
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 214,000
ft2
Annual Production 4,000,000,000
pieces
Production Hrs. Annual 8,640
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $338,690 9,336,460
kWh
Natural Gas $267,558 74,360
MMBtu
Other Energy $167,967 72,494
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $698,612 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,323

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,720 $12,717 $7,720
212,778
kWh
- - - -
02 2.4133: Use most efficient type of electric motors $453 $3,281 $453
12,603
kWh
- - - -
03 2.4323: Use optimum size and capacity equipment $1,856 $2,388 $1,856
51,583
kWh
- - - -
04 2.8113: Purchase gas directly from a contract gas supplier $39,032 $2,500 - - - - $39,032
05 3.4116: Meter recycled water (to reduce sewer charges) $8,150 $1,100 - $8,150
-
Tgal
- - -
06 3.5311: Recover and reuse waste material $48,600 $25,000 - - $48,600
-
lb
- -
07 3.2176: Increase use of automation $592,801 $1,500,000 $(-5,599.0)
(-155,627)
kWh
- - $598,400 -
TOTAL RECOMMENDED $698,612 $1,546,986 $4,430
121,337
kWh
$8,150
-
Tgal
$48,600
-
lb
$598,400 $39,032
TOTAL IMPLEMENTED $16,323 $17,098 $8,173
225,381
kWh
$8,150
-
Tgal
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs