ITAC Assessment: KU0426
ITAC logo
ITAC Assessment: KU0426
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Periodicals and books
NAICS
n/a
SIC 2721: Periodicals: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 144,000
ft2
Annual Production 2,400,000
pieces
Production Hrs. Annual 4,758
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,297 1,817,409
kWh
Natural Gas $4,783 1,041
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,771 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,696

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.2623: Minimize condenser cooling water temperature $4,888 $2,500 $4,888
114,889
kWh
02 2.7124: Make a practice of turning off lights when not needed $1,222 - $1,222
28,722
kWh
03 2.7132: Install timers on light switches in little used areas $399 $68 $399
9,379
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $75 $288 $75
1,758
kWh
05 2.4221: Install compressor air intakes in coolest locations $187 $260 $187
4,396
kWh
TOTAL RECOMMENDED $6,771 $3,116 $6,771
159,144
kWh
TOTAL IMPLEMENTED $1,696 $356 $1,696
39,859
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs