Assessment Year | 1994 |
---|---|
Principal Product | Aircraft Refueling Equipment |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
84,773
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 2,151
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,702 | 305,100 |
kWh
|
$0.081 |
Natural Gas | $6,824 | 1,422 |
MMBtu
|
$4.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,890 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,751 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $502 | $3,380 | - |
$502
-
MMBtu
|
|
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $148 | $1,575 | - |
$148
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $593 | $1,703 |
$593
7,327
kWh
|
- | |
04 | 2.7135: Install occupancy sensors | $275 | $1,300 |
$275
3,517
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $166 | $416 |
$166
2,052
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $95 | $200 |
$95
1,172
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $71 | $128 |
$71
879
kWh
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $451 | $608 |
$451
5,569
kWh
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $332 | $110 |
$332
4,103
kWh
|
- | |
10 | 2.2437: Recover waste heat from equipment | $139 | $80 |
$48
586
kWh
|
$91
-
MMBtu
|
|
11 | 2.6121: Reduce hot water temperature to the minimum required | $118 | - | - |
$118
-
MMBtu
|
|
TOTAL RECOMMENDED | $2,890 | $9,500 |
$2,031
25,205
kWh
|
$859
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,751 | $9,420 |
$1,983
24,619
kWh
|
$768
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs