| Assessment Year | 1993 |
|---|---|
| Principal Product | Cargo Control Products |
| NAICS |
n/a
|
| SIC | 2298: Cordage and Twine |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
40,000
ft2
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $29,703 | 529,601 |
kWh
|
$0.056 |
| Natural Gas | $18,005 | 3,277 |
MMBtu
|
$5.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,318 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,999 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $2,468 | $10,400 |
$(-1,069.0)
(-19,050)
kWh
|
$3,537
-
MMBtu
|
- | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $1,044 | $1,000 |
$411
7,327
kWh
|
$633
-
MMBtu
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,703 | $520 |
$893
15,826
kWh
|
- | $810 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,173 | $832 |
$148
2,638
kWh
|
- | $1,025 | |
| 05 | 2.7135: Install occupancy sensors | $453 | $600 |
$453
8,206
kWh
|
- | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $329 | $30 |
$329
5,862
kWh
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $148 | $150 |
$148
2,638
kWh
|
- | - | |
| TOTAL RECOMMENDED | $7,318 | $13,532 |
$1,313
23,447
kWh
|
$4,170
-
MMBtu
|
$1,835 | ||
| TOTAL IMPLEMENTED | $2,999 | $2,462 |
$1,341
24,033
kWh
|
$633
-
MMBtu
|
$1,025 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs