ITAC Assessment: KU0414
ITAC logo
ITAC Assessment: KU0414
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Cargo Control Products
NAICS
n/a
SIC 2298: Cordage and Twine
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 40,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $29,703 529,601
kWh
Natural Gas $18,005 3,277
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,318 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,999

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7243: Improve air circulation with destratification fans / other methods $2,468 $10,400 $(-1,069.0)
(-19,050)
kWh
$3,537
-
MMBtu
-
02 2.7224: Reduce space conditioning during non-working hours $1,044 $1,000 $411
7,327
kWh
$633
-
MMBtu
-
03 2.7111: Reduce illumination to minimum necessary levels $1,703 $520 $893
15,826
kWh
- $810
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,173 $832 $148
2,638
kWh
- $1,025
05 2.7135: Install occupancy sensors $453 $600 $453
8,206
kWh
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $329 $30 $329
5,862
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $148 $150 $148
2,638
kWh
- -
TOTAL RECOMMENDED $7,318 $13,532 $1,313
23,447
kWh
$4,170
-
MMBtu
$1,835
TOTAL IMPLEMENTED $2,999 $2,462 $1,341
24,033
kWh
$633
-
MMBtu
$1,025
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs