| Assessment Year | 1993 |
|---|---|
| Principal Product | Feedwater Heaters |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
60,000
ft2
|
| Annual Production | 40
pieces
|
| Production Hrs. Annual | 5,304
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $123,065 | 2,583,236 |
kWh
|
$0.048 |
| Natural Gas | $42,314 | 10,864 |
MMBtu
|
$3.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,691 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,080 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $2,080 | $780 |
$2,080
43,669
kWh
|
- | |
| 02 | 2.4314: Use synthetic lubricant | $1,675 | - |
$1,675
35,170
kWh
|
- | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $271 | - |
$84
1,758
kWh
|
$187
-
MMBtu
|
|
| 04 | 2.7135: Install occupancy sensors | $665 | $1,900 |
$665
14,068
kWh
|
- | |
| TOTAL RECOMMENDED | $4,691 | $2,680 |
$4,504
94,665
kWh
|
$187
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,080 | $780 |
$2,080
43,669
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs