Assessment Year | 1992 |
---|---|
Principal Product | PROCESSED CHEESE |
NAICS |
n/a
|
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $50 M to 100M |
# of Employees | 220 |
Plant Area |
n/a
|
Annual Production | 60,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $193,395 | 3,755,569 |
kWh
|
$0.051 |
Natural Gas | $59,762 | 17,033 |
MMBtu
|
$3.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $11,710 | $6,000 |
$11,710
227,433
kWh
|
- | |
02 | 2.4322: Use or replace with energy efficient substitutes | $7,473 | $22,500 | - |
$7,473
-
MMBtu
|
|
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,987 | $150 | - |
$1,987
-
MMBtu
|
|
04 | 2.1123: Install automatic stack damper | $1,794 | $2,525 | - |
$1,794
-
MMBtu
|
|
05 | 2.2522: Isolate hot or cold equipment | $1,192 | $300 |
$1,192
23,154
kWh
|
- | |
06 | 2.6232: Install set-back timers | $770 | $1,900 |
$770
14,947
kWh
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $377 | $310 |
$377
7,327
kWh
|
- | |
TOTAL RECOMMENDED | $25,303 | $33,685 |
$14,049
272,861
kWh
|
$11,254
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs