| Assessment Year | 1992 |
|---|---|
| Principal Product | PROCESSED CHEESE |
| NAICS |
n/a
|
| SIC | 2022: Natural, Processed, and Imitation Cheese |
| Sales Range | $50 M to 100M |
| # of Employees | 220 |
| Plant Area |
n/a
|
| Annual Production | 60,000,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $193,395 | 3,755,569 |
kWh
|
$0.051 |
| Natural Gas | $59,762 | 17,033 |
MMBtu
|
$3.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $11,710 | $6,000 |
$11,710
227,433
kWh
|
- | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $7,473 | $22,500 | - |
$7,473
-
MMBtu
|
|
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,987 | $150 | - |
$1,987
-
MMBtu
|
|
| 04 | 2.1123: Install automatic stack damper | $1,794 | $2,525 | - |
$1,794
-
MMBtu
|
|
| 05 | 2.2522: Isolate hot or cold equipment | $1,192 | $300 |
$1,192
23,154
kWh
|
- | |
| 06 | 2.6232: Install set-back timers | $770 | $1,900 |
$770
14,947
kWh
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $377 | $310 |
$377
7,327
kWh
|
- | |
| TOTAL RECOMMENDED | $25,303 | $33,685 |
$14,049
272,861
kWh
|
$11,254
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs