ITAC Assessment: KU0352
ITAC logo
ITAC Assessment: KU0352
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product AIR FILTER CANISTERS
NAICS
n/a
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area
n/a
Annual Production 250,000
pieces
Production Hrs. Annual 3,840
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $281,040 3,827,960
kWh
Natural Gas $93,985 31,927
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,004 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,004

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6232: Install set-back timers $4,777 $2,460 $4,777
65,064
kWh
- -
02 2.7111: Reduce illumination to minimum necessary levels $796 $360 $796
10,844
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $409 - $435
5,862
kWh
- $(-26.0)
04 2.2437: Recover waste heat from equipment $3,963 $3,800 - $3,963
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,658 $500 $3,658
49,824
kWh
- -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,322 - $1,592
21,688
kWh
$(-270.0)
-
MMBtu
-
07 2.1213: Direct warmest air to combustion intake $735 $2,200 - $735
-
MMBtu
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $344 - $344
4,689
kWh
- -
TOTAL RECOMMENDED $16,004 $9,320 $11,602
157,971
kWh
$4,428
-
MMBtu
$(-26.0)
TOTAL IMPLEMENTED $16,004 $9,320 $11,602
157,971
kWh
$4,428
-
MMBtu
$(-26.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs