Assessment Year | 1991 |
---|---|
Principal Product | IND. AIR COMPRESSORS |
NAICS |
n/a
|
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $50 M to 100M |
# of Employees | 204 |
Plant Area |
n/a
|
Annual Production | 6,120
pieces
|
Production Hrs. Annual | 5,712
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $387,993 | 7,465,416 |
kWh
|
$0.052 |
Natural Gas | $76,770 | 14,411 |
MMBtu
|
$5.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,909 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $108,909 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $21,491 | $19,500 | - |
$21,491
-
MMBtu
|
- | |
02 | 2.7245: Use direct air supply to exhaust hoods | $15,055 | $18,000 |
$3,137
60,375
kWh
|
$11,918
-
MMBtu
|
- | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $12,114 | $27,600 |
$(-838.0)
(-16,120)
kWh
|
$12,952
-
MMBtu
|
- | |
04 | 2.2437: Recover waste heat from equipment | $9,818 | $3,800 | - |
$9,818
-
MMBtu
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $22,099 | $22,000 |
$22,099
425,264
kWh
|
- | - | |
06 | 2.5194: Redesign process | $10,585 | $25,200 |
$10,585
145,076
kWh
|
- | - | |
07 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,650 | $17,100 |
$5,650
108,734
kWh
|
- | - | |
08 | 2.3512: De-energize excess transformer capacity | $1,112 | - |
$1,112
21,395
kWh
|
- | - | |
09 | 2.6232: Install set-back timers | $899 | $1,000 |
$899
17,292
kWh
|
- | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $366 | - |
$366
7,034
kWh
|
- | - | |
11 | 3.4115: Recover and reuse cooling water | $9,720 | $5,340 |
$(-990.0)
(-19,050)
kWh
|
- | $10,710 | |
TOTAL RECOMMENDED | $108,909 | $139,540 |
$42,020
750,000
kWh
|
$56,179
-
MMBtu
|
$10,710 | ||
TOTAL IMPLEMENTED | $108,909 | $139,540 |
$42,020
750,000
kWh
|
$56,179
-
MMBtu
|
$10,710 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs