| Assessment Year | 1990 |
|---|---|
| Principal Product | GLASS - FLAT & TEMPERED |
| NAICS |
n/a
|
| SIC | 3211: Flat Glass |
| Sales Range | $10 M to 50M |
| # of Employees | 255 |
| Plant Area |
n/a
|
| Annual Production | 145,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $732,875 | 21,292,790 |
kWh
|
$0.034 |
| Natural Gas | $2,467,442 | 1,023,469 |
MMBtu
|
$2.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $218,918 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $162,250 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $1,985 | $400 |
$1,985
48,945
kWh
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $16,590 | $15,212 |
$16,590
410,317
kWh
|
- | |
| 03 | 2.3212: Optimize plant power factor | $66,605 | $54,000 |
$66,605
-
kWh
|
- | |
| 04 | 2.6223: Schedule use of elevators to conserve energy | $1,365 | $200 |
$1,365
33,705
kWh
|
- | |
| 05 | 2.2444: Use hot process fluids to preheat incoming process fluids | $35,795 | $40,000 |
$12,667
313,306
kWh
|
$23,128
-
MMBtu
|
|
| 06 | 2.1123: Install automatic stack damper | $1,690 | $3,000 | - |
$1,690
-
MMBtu
|
|
| 07 | 2.2444: Use hot process fluids to preheat incoming process fluids | $18,888 | $13,080 |
$(-1,792.0)
(-44,256)
kWh
|
$20,680
-
MMBtu
|
|
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $76,000 | $50,000 | - |
$76,000
-
MMBtu
|
|
| TOTAL RECOMMENDED | $218,918 | $175,892 |
$97,420
762,017
kWh
|
$121,498
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $162,250 | $122,412 |
$84,560
444,022
kWh
|
$77,690
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs