| Assessment Year | 1990 |
|---|---|
| Principal Product | STEEL ROLLERS |
| NAICS |
n/a
|
| SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
| Sales Range | $50 M to 100M |
| # of Employees | 325 |
| Plant Area |
n/a
|
| Annual Production | 7,500
ton
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $590,338 | 12,894,490 |
kWh
|
$0.046 |
| Natural Gas | $259,979 | 86,833 |
MMBtu
|
$2.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $154,321 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $120,912 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,571 | $25,000 |
$17,032
283,705
kWh
|
$(-2,461.0)
-
MMBtu
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $11,218 | $14,000 |
$12,372
141,852
kWh
|
$(-1,154.0)
-
MMBtu
|
- | |
| 03 | 2.7492: Use proper thickness of insulation on building envelope | $3,489 | $8,000 | - |
$3,489
-
MMBtu
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $7,341 | $6,000 |
$7,341
256,155
kWh
|
- | - | |
| 05 | 2.6241: Reduce temperature of process equipment when on standby | $7,638 | - |
$7,638
-
kWh
|
- | - | |
| 06 | 2.3191: Use demand controller or load shedder | $16,450 | $500 |
$16,450
-
kWh
|
- | - | |
| 07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $8,223 | $33,000 |
$13,650
300,117
kWh
|
$(-5,427.0)
-
MMBtu
|
- | |
| 08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $83,411 | $150,000 |
$111,500
1,000,293
kWh
|
$(-18,089.0)
-
MMBtu
|
$(-10,000.0) | |
| 09 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,980 | - |
$1,980
89,977
kWh
|
- | - | |
| TOTAL RECOMMENDED | $154,321 | $236,500 |
$187,963
2,072,099
kWh
|
$(-23,642.0)
-
MMBtu
|
$(-10,000.0) | ||
| TOTAL IMPLEMENTED | $120,912 | $230,000 |
$154,554
1,725,967
kWh
|
$(-23,642.0)
-
MMBtu
|
$(-10,000.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs