Assessment Year | 2003 |
---|---|
Principal Product | Portable Fans and Heaters |
NAICS | 333612: Speed Changer, Industrial High-Speed Drive, and Gear Manufacturing |
SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
428,000
ft2
|
Annual Production | 4,000,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $253,897 | 8,729,852 |
kWh
|
$0.029 |
Electricity Demand | $61,072 | 17,012 |
kW-mo/yr
|
$3.59 |
Electricity Fees | $293,010 | - |
|
- |
Natural Gas | $258,877 | 54,797 |
MMBtu
|
$4.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $270,257 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $114,500 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,895 | $46,610 |
$19,136
308,650
kWh
|
$1,518
-
kW-mo/yr
|
- | $(-1,205.0) | $(-554.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,127 | $2,716 |
$701
11,300
kWh
|
$124
-
kW-mo/yr
|
- | $178 | $124 | |
03 | 2.7135: Install occupancy sensors | $8,874 | $22,864 |
$8,669
139,829
kWh
|
$205
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $51,638 | $160,788 |
$42,670
688,063
kWh
|
$4,466
-
kW-mo/yr
|
- | - | $4,502 | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $1,377 | - |
$1,377
22,210
kWh
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $56,367 | $4,200 |
$52,222
842,290
kWh
|
$4,145
-
kW-mo/yr
|
- | - | - | |
07 | 2.6218: Turn off equipment when not in use | $58,133 | - |
$58,133
937,629
kWh
|
- | - | - | - | |
08 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $73,846 | $613,200 | - | - |
$73,846
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $270,257 | $850,378 |
$182,908
2,949,971
kWh
|
$10,458
-
kW-mo/yr
|
$73,846
-
MMBtu
|
$(-1,027.0) | $4,072 | ||
TOTAL IMPLEMENTED | $114,500 | $4,200 |
$110,355
1,779,919
kWh
|
$4,145
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs