| Assessment Year | 1989 |
|---|---|
| Principal Product | AMBULANCES, STEPLIFTS |
| NAICS |
n/a
|
| SIC | 3799: Transportation Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 240 |
| Plant Area |
n/a
|
| Annual Production | 2,700
pieces
|
| Production Hrs. Annual | 2,520
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,936 | 743,259 |
kWh
|
$0.067 |
| Natural Gas | $20,147 | 7,327 |
MMBtu
|
$2.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,013 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,137 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $394 | $261 |
$394
5,862
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $1,945 | $1,800 |
$768
11,430
kWh
|
$1,177
-
MMBtu
|
|
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $669 | - |
$669
9,965
kWh
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $82 | $117 |
$82
1,172
kWh
|
- | |
| 05 | 2.6121: Reduce hot water temperature to the minimum required | $500 | - |
$472
7,034
kWh
|
$28
-
MMBtu
|
|
| 06 | 2.2437: Recover waste heat from equipment | $242 | $350 | - |
$242
-
MMBtu
|
|
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $886 | $150 |
$886
13,189
kWh
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $295 | $650 |
$295
4,396
kWh
|
- | |
| TOTAL RECOMMENDED | $5,013 | $3,328 |
$3,566
53,048
kWh
|
$1,447
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,137 | $267 |
$2,109
31,360
kWh
|
$28
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs