ITAC Assessment: KU0286
ITAC logo
ITAC Assessment: KU0286
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product INJECTION MOLDED PRODUCT
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 10,000,000
lb
Production Hrs. Annual 6,720
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $407,361 7,031,946
kWh
Natural Gas $32,465 9,396
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,424 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,424

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,513 $6,446 $3,513
60,668
kWh
-
02 2.6121: Reduce hot water temperature to the minimum required $235 - $204
3,517
kWh
$31
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,139 $500 $3,139
54,220
kWh
-
04 2.1123: Install automatic stack damper $6,820 $5,625 - $6,820
-
MMBtu
05 2.4133: Use most efficient type of electric motors $2,698 $1,800 $2,698
46,600
kWh
-
06 2.2614: Use cooling tower or economizer to replace chiller cooling $14,815 $20,000 $14,815
255,862
kWh
-
07 2.7447: Install vinyl strip / high speed / air curtain doors $204 $250 - $204
-
MMBtu
TOTAL RECOMMENDED $31,424 $34,621 $24,369
420,867
kWh
$7,055
-
MMBtu
TOTAL IMPLEMENTED $31,424 $34,621 $24,369
420,867
kWh
$7,055
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs