ITAC Assessment: LS0123
ITAC logo
ITAC Assessment: LS0123
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Hotel
NAICS 721110: Hotels (except Casino Hotels) and Motels
SIC 7011: Hotels and Motels
Sales Range less than $500
k
# of Employees 50
Plant Area 53,417
ft2
Annual Production 1
units
Production Hrs. Annual 8,760
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $183,932 2,279,000
kWh
Electricity Demand $50,919 4,567
kW-mo/yr
Natural Gas $31,132 2,775
MMBtu
TOTAL YEARLY COSTS $265,983
RECOMMENDED SAVINGS* $31,624 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,624

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $106 $157 $106
1,314
kWh
-
02 2.1224: Replace boiler $17,372 $62,400 - $17,372
-
MMBtu
03 2.7226: Use computer programs to optimize hvac performance $14,146 $54,880 $14,146
174,645
kWh
-
TOTAL RECOMMENDED $31,624 $117,437 $14,252
175,959
kWh
$17,372
-
MMBtu
TOTAL IMPLEMENTED $31,624 $117,437 $14,252
175,959
kWh
$17,372
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs