ITAC Assessment: KU0270
ITAC logo
ITAC Assessment: KU0270
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product RECREATIONAL VEHICLES
NAICS
n/a
SIC 3716: Motor Homes
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area
n/a
Annual Production 750
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,587 1,322,098
kWh
Natural Gas $42,845 15,315
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,612 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,698

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,368 $16,108 $7,368
108,734
kWh
- -
02 2.4239: Eliminate or reduce compressed air usage $2,463 $1,660 $2,463
36,342
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,463 $775 $2,463
36,342
kWh
- -
04 2.2437: Recover waste heat from equipment $1,151 $1,000 - $1,151
-
MMBtu
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $755 $940 $755
11,137
kWh
- -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,192 - $1,692
-
kWh
- $(-500.0)
07 2.7447: Install vinyl strip / high speed / air curtain doors $4,329 $7,575 - $4,329
-
MMBtu
-
08 2.7261: Install timers and/or thermostats $4,749 $15 $179
2,638
kWh
$4,570
-
MMBtu
-
09 2.7224: Reduce space conditioning during non-working hours $1,221 - - $1,221
-
MMBtu
-
10 3.4113: Treat and reuse rinse waters $2,921 $4,700 $60
879
kWh
- $2,861
TOTAL RECOMMENDED $28,612 $32,773 $14,980
196,072
kWh
$11,271
-
MMBtu
$2,361
TOTAL IMPLEMENTED $8,698 $10,290 $3,218
47,479
kWh
$5,480
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs