ITAC Assessment: KU0239
ITAC logo
ITAC Assessment: KU0239
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product PRINTERS, BOOKS, PUBLICITY MATERIAL
NAICS
n/a
SIC 2731: Books: Publishing, or Publishing and Printing
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area
n/a
Annual Production 756,000
pieces
Production Hrs. Annual 1,820
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,857 836,460
kWh
Natural Gas $8,538 2,332
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,984 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,978

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $5,811 $300 $3,096
48,945
kWh
$2,715
-
MMBtu
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $516 - $666
-
kWh
- $(-150.0)
03 2.1233: Analyze flue gas for proper air/fuel ratio $392 - - $542
-
MMBtu
$(-150.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $410 $79 $410
6,448
kWh
- -
05 2.1222: Install turbulators $318 $500 - $318
-
MMBtu
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $222 $50 $222
3,517
kWh
- -
07 2.2437: Recover waste heat from equipment $172 $50 - $172
-
MMBtu
-
08 2.6121: Reduce hot water temperature to the minimum required $143 - - $143
-
MMBtu
-
TOTAL RECOMMENDED $7,984 $979 $4,394
58,910
kWh
$3,890
-
MMBtu
$(-300.0)
TOTAL IMPLEMENTED $6,978 $429 $3,728
58,910
kWh
$3,400
-
MMBtu
$(-150.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs