Assessment Year | 2003 |
---|---|
Principal Product | Water Valves |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
60,000
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $758,286 | 7,061,881 |
kWh
|
$0.11 |
Electricity Demand | $208,755 | 16,890 |
kW-mo/yr
|
$12.36 |
Natural Gas | $4,911 | 669 |
MMBtu
|
$7.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $324,993 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $189,068 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $4,760 | $300 |
$3,833
35,921
kWh
|
$927
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $731 | $100 |
$590
5,467
kWh
|
$141
-
kW-mo/yr
|
- | - | - | |
03 | 2.2511: Insulate bare equipment | $14,715 | $5,241 |
$11,969
112,706
kWh
|
$2,746
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $7,493 | $8,340 |
$7,493
70,599
kWh
|
- | - | - | - | |
05 | 2.2314: Replace heat treating oven with more efficient unit | $4,415 | $3,108 |
$2,892
27,000
kWh
|
$678
-
kW-mo/yr
|
- |
$845
-
MMBtu
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,834 | $23,076 |
$11,253
105,958
kWh
|
$2,581
-
kW-mo/yr
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $173,236 | $360,625 |
$140,850
1,323,124
kWh
|
$32,386
-
kW-mo/yr
|
- | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,606 | $9,060 |
$3,472
33,070
kWh
|
$1,134
-
kW-mo/yr
|
- | - | - | |
09 | 2.7132: Install timers on light switches in little used areas | $850 | $2,280 |
$695
6,264
kWh
|
$155
-
kW-mo/yr
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,735 | $23,266 |
$4,569
42,984
kWh
|
$1,166
-
kW-mo/yr
|
- | - | - | |
11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,000 | $16,250 | - | - | - | - |
$7,000
-
lb
|
|
12 | 2.3212: Optimize plant power factor | $5,154 | $11,258 | - | - | $5,154 | - | - | |
13 | 2.8114: Change rate schedules or other changes in utility service | $82,464 | $264,000 | - | - | $82,464 | - | - | |
TOTAL RECOMMENDED | $324,993 | $726,904 |
$187,616
1,763,093
kWh
|
$41,914
-
kW-mo/yr
|
$87,618 |
$845
-
MMBtu
|
$7,000
-
lb
|
||
TOTAL IMPLEMENTED | $189,068 | $393,351 |
$153,314
1,440,566
kWh
|
$35,754
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs