Assessment Year | 2018 |
---|---|
Principal Product | Semi-Trailers |
NAICS | 336212: Truck Trailer Manufacturing |
SIC | 3715: Truck Trailers |
Sales Range | $10 M to 50M |
# of Employees | 83 |
Plant Area |
68,770
ft2
|
Annual Production | 500
units
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $61,111 | 754,457 |
kWh
|
$0.081 | |
Electricity Demand | $71,463 | 3,408 |
kW-mo/yr
|
$20.97 | |
Natural Gas | $30,426 | 6,508 |
MMBtu
|
$4.68 | |
Waste Disposal Costs | |||||
Water Usage | $4,355 | 2,329 |
Tgal
|
$1.87 | |
Water Disposal | $7,430 | 2,329 |
Tgal
|
$3.19 | |
TOTAL YEARLY COSTS | $174,784 | ||||
RECOMMENDED SAVINGS* | $30,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $24,239 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,239 | $33,526 |
$10,726
132,418
kWh
|
$13,048
-
kW-mo/yr
|
- | $465 | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $5,242 | $10,000 |
$(-158.0)
(-1,956)
kWh
|
- | - | - | $5,400 | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $571 | - |
$571
7,050
kWh
|
- | - | - | - | |
04 | 3.4155: Meter waste water | $319 | - | - | - |
$319
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $30,371 | $43,526 |
$11,139
137,512
kWh
|
$13,048
-
kW-mo/yr
|
$319
-
Tgal
|
$465 | $5,400 | ||
TOTAL IMPLEMENTED | $24,239 | $33,526 |
$10,726
132,418
kWh
|
$13,048
-
kW-mo/yr
|
- | $465 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs