Assessment Year | 1987 |
---|---|
Principal Product | PRINTING INK |
NAICS |
n/a
|
SIC | 2893: Printing Ink |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
n/a
|
Annual Production | 804,000
lb
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $46,909 | 529,308 |
kWh
|
$0.089 |
Natural Gas | $5,582 | 1,371 |
MMBtu
|
$4.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,894 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,436 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,838 | $600 |
$5,965
65,064
kWh
|
$(-1,127.0)
-
MMBtu
|
|
02 | 2.1123: Install automatic stack damper | $399 | $250 | - |
$399
-
MMBtu
|
|
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,921 | $2,000 |
$2,389
26,964
kWh
|
$(-468.0)
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $407 | $250 | - |
$407
-
MMBtu
|
|
05 | 2.1123: Install automatic stack damper | $313 | $250 | - |
$313
-
MMBtu
|
|
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,203 | $200 |
$1,410
15,826
kWh
|
$(-207.0)
-
MMBtu
|
|
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $390 | $40 |
$390
4,396
kWh
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $519 | - |
$519
5,862
kWh
|
- | |
09 | 2.4312: Improve lubrication practices | $597 | - |
$597
6,741
kWh
|
- | |
10 | 2.7261: Install timers and/or thermostats | $3,307 | $157 |
$519
5,862
kWh
|
$2,788
-
MMBtu
|
|
TOTAL RECOMMENDED | $13,894 | $3,747 |
$11,789
130,715
kWh
|
$2,105
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,436 | $607 |
$2,448
27,550
kWh
|
$2,988
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs