| Assessment Year | 1987 |
|---|---|
| Principal Product | MEDICAL EQUIPMENT |
| NAICS |
n/a
|
| SIC | 3534: Elevators and Moving Stairways |
| Sales Range | $10 M to 50M |
| # of Employees | 95 |
| Plant Area |
n/a
|
| Annual Production | 7,200
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,842 | 719,812 |
kWh
|
$0.065 |
| Natural Gas | $14,128 | 4,364 |
MMBtu
|
$3.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,315 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,340 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.5194: Redesign process | $8,861 | $5,000 |
$229
3,517
kWh
|
$557
-
MMBtu
|
$8,075 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,771 | $4,019 |
$1,771
27,257
kWh
|
- | - | |
| 03 | 2.2511: Insulate bare equipment | $1,447 | $700 |
$1,602
24,619
kWh
|
$(-155.0)
-
MMBtu
|
- | |
| 04 | 2.7261: Install timers and/or thermostats | $1,030 | - |
$534
8,206
kWh
|
$496
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $667 | $275 |
$667
10,258
kWh
|
- | - | |
| 06 | 2.2514: Cover open tanks | $262 | $200 | - |
$262
-
MMBtu
|
- | |
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $125 | - | - |
$165
-
MMBtu
|
$(-40.0) | |
| 08 | 2.2437: Recover waste heat from equipment | $152 | $290 | - |
$152
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $14,315 | $10,484 |
$4,803
73,857
kWh
|
$1,477
-
MMBtu
|
$8,035 | ||
| TOTAL IMPLEMENTED | $3,340 | $4,509 |
$2,305
35,463
kWh
|
$1,075
-
MMBtu
|
$(-40.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs