Assessment Year | 1986 |
---|---|
Principal Product | WIRE HANGERS |
NAICS |
n/a
|
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 6,000
ton
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,011 | 1,466,882 |
kWh
|
$0.076 |
Natural Gas | $43,158 | 10,822 |
MMBtu
|
$3.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,532 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,750 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $50,936 | $300,000 |
$90,764
1,199,883
kWh
|
$(-39,828.0)
-
MMBtu
|
- | |
02 | 2.2444: Use hot process fluids to preheat incoming process fluids | $8,720 | $3,000 | - |
$8,720
-
MMBtu
|
- | |
03 | 2.4312: Improve lubrication practices | $2,017 | $1,600 |
$2,017
26,671
kWh
|
- | - | |
04 | 2.1123: Install automatic stack damper | $1,220 | $700 | - |
$1,220
-
MMBtu
|
- | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $715 | - | - |
$715
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $335 | - | - |
$535
-
MMBtu
|
$(-200.0) | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $732 | $30 |
$732
9,672
kWh
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $576 | $50 |
$576
7,620
kWh
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $155 | $100 |
$155
2,052
kWh
|
- | - | |
10 | 2.6121: Reduce hot water temperature to the minimum required | $126 | - | - |
$126
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $65,532 | $305,480 |
$94,244
1,245,898
kWh
|
$(-28,512.0)
-
MMBtu
|
$(-200.0) | ||
TOTAL IMPLEMENTED | $5,750 | $2,480 |
$3,480
46,015
kWh
|
$2,470
-
MMBtu
|
$(-200.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs