Assessment Year | 1985 |
---|---|
Principal Product | TRANSFORMERS,INDUCTORS |
NAICS |
n/a
|
SIC | 3677: Electronic Coils, Transformers, and Other Inductors |
Sales Range | $1 M to 5M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 150,000
pieces
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $23,358 | 352,579 |
kWh
|
$0.066 |
Natural Gas | $3,035 | 787 |
MMBtu
|
$3.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,508 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,085 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $1,642 | $500 |
$1,067
16,120
kWh
|
$575
-
MMBtu
|
|
02 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $1,693 | $764 |
$446
6,741
kWh
|
$1,247
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $990 | $1,450 |
$990
14,947
kWh
|
- | |
04 | 2.2515: Use optimum thickness insulation | $730 | $1,138 |
$834
12,603
kWh
|
$(-104.0)
-
MMBtu
|
|
05 | 2.2514: Cover open tanks | $279 | $60 |
$329
4,982
kWh
|
$(-50.0)
-
MMBtu
|
|
06 | 2.6121: Reduce hot water temperature to the minimum required | $174 | - | - |
$174
-
MMBtu
|
|
TOTAL RECOMMENDED | $5,508 | $3,912 |
$3,666
55,393
kWh
|
$1,842
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,085 | $2,010 |
$2,386
36,049
kWh
|
$699
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs