| Assessment Year | 1985 |
|---|---|
| Principal Product | MATTRESSES & FOUNDATIONS |
| NAICS |
n/a
|
| SIC | 2515: Mattresses, Foundations, and Convertible Beds |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,324 | 490,035 |
kWh
|
$0.066 |
| Natural Gas | $31,294 | 6,386 |
MMBtu
|
$4.90 |
| Other Energy | $23,958 | 2,958 |
MMBtu
|
$8.10 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,446 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,340 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $972 | - | - |
$1,372
-
MMBtu
|
- | $(-400.0) | |
| 02 | 2.7261: Install timers and/or thermostats | $4,851 | $2,700 | - |
$4,851
-
MMBtu
|
- | - | |
| 03 | 2.1123: Install automatic stack damper | $1,700 | $1,950 | - |
$1,700
-
MMBtu
|
- | - | |
| 04 | 2.7211: Clean and maintain refrigerant condensers and towers | $110 | - |
$135
2,052
kWh
|
- | - | $(-25.0) | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $754 | $200 |
$754
11,430
kWh
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,218 | $700 |
$1,218
18,464
kWh
|
- | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $174 | $10 |
$174
2,638
kWh
|
- | - | - | |
| 08 | 2.3212: Optimize plant power factor | $1,714 | $4,000 |
$1,714
-
kWh
|
- | - | - | |
| 09 | 2.4312: Improve lubrication practices | $232 | $200 |
$232
3,517
kWh
|
- | - | - | |
| 10 | 2.8223: Add air shields to trucks to increase fuel mileage | $721 | - | - | - |
$721
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $12,446 | $9,760 |
$4,227
38,101
kWh
|
$7,923
-
MMBtu
|
$721
-
MMBtu
|
$(-425.0) | ||
| TOTAL IMPLEMENTED | $10,340 | $7,600 |
$3,821
31,946
kWh
|
$6,223
-
MMBtu
|
$721
-
MMBtu
|
$(-425.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs