| Assessment Year | 1985 |
|---|---|
| Principal Product | SEAT LIFT CHAIRS |
| NAICS |
n/a
|
| SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
| Sales Range | $5 M to 10M |
| # of Employees | 110 |
| Plant Area |
n/a
|
| Annual Production | 12,000
pieces
|
| Production Hrs. Annual | 2,400
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $14,878 | 178,781 |
kWh
|
$0.083 |
| Natural Gas | $4,146 | 841 |
MMBtu
|
$4.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,458 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,426 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $3,195 | $3,957 |
$3,195
38,394
kWh
|
- | - | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $182 | - | - |
$232
-
MMBtu
|
$(-50.0) | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $49 | $40 |
$49
586
kWh
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $32 | $65 |
$32
586
kWh
|
- | - | |
| TOTAL RECOMMENDED | $3,458 | $4,062 |
$3,276
39,566
kWh
|
$232
-
MMBtu
|
$(-50.0) | ||
| TOTAL IMPLEMENTED | $3,426 | $3,997 |
$3,244
38,980
kWh
|
$232
-
MMBtu
|
$(-50.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs