ITAC Assessment: KU0161
ITAC logo
ITAC Assessment: KU0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product SEAT LIFT CHAIRS
NAICS
n/a
SIC 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies
Sales Range $5
M
to 10
M
# of Employees 110
Plant Area
n/a
Annual Production 12,000
pieces
Production Hrs. Annual 2,400
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,878 178,781
kWh
Natural Gas $4,146 841
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,458 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,426

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $3,195 $3,957 $3,195
38,394
kWh
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $182 - - $232
-
MMBtu
$(-50.0)
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $49 $40 $49
586
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $32 $65 $32
586
kWh
- -
TOTAL RECOMMENDED $3,458 $4,062 $3,276
39,566
kWh
$232
-
MMBtu
$(-50.0)
TOTAL IMPLEMENTED $3,426 $3,997 $3,244
38,980
kWh
$232
-
MMBtu
$(-50.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs